The daily test of your patience behind the wheel is expected to end this week, until connecting link work picks up in the spring, at least.
City engineering manager Scott Collin says paving the two eastbound lanes alongside Hollinger Park will finish Monday, with line painting to happen Tuesday and Wednesday.
Temporary lane closures are expected along the sides the rest of the week, while things are safely restored for winter.
And Collin says steel poles for streetlights and traffic signals haven’t arrived yet, but that work can happen any time.
“All the bases and everything’s there for them to be installed, we’re just physically waiting for the material to arrive.”
The stretch of road just outside Porcupine is also expected to wrap up this week.
Collin says paving is done.
“They’ll be working this week to widen the entrances and get the entrances to the side streets ready to be paved,” he notes, “and we expect line painting to be completed on that segment later this week.”
Collin acknowledges drivers’ frustrations and is thankful for any patience.